China Trade Center, 2 Boylston Street - Mechanical System Improvements

The Mechanical System Improvements Project generally consists of new heating, cooling and ventilation air plants with the associated electrical and structural modifications necessary.  The work includes, but is not limited to, removing the existing equipment and providing and installing the following new equipment:

1.) Energy Recovery Unit (ERV) and Cooling towers (located on roof)  

2.) Condensing boilers (located in basement).  

Mechanical plumbing, electrical subpanel, baseboard radiation covers, chimney flue, duct riser with operable dampers, building management system modifications, new concrete slabs, structural roof reinforcement, drywall demolition, pre-fabricated metal panel head house installation are included in the work.  

Required with all general and sub bids are MA Department of Workforce Development 'Sponsor Verification' form, DCAM Eligibility Certificate and update statement, and compliance with Boston Jobs Policy.

Filed Sub-bid categories are HVAC, Structural Steel Framing, Electrical and Plumbing.

Type Bid
Status Awarded
Due Date 07/01/2016 10:00
Pre Bid Meeting Date 06/07/2016 10:00
Sub Bids Due 06/17/2016 10:00
Awarded Date 08/03/2016
Awarded Company Enterprise Equipment Co., Inc.
Contract Value $1,745,350
Contact [email protected]


RESPONDENTS
CompanySubmissionValue
Enterprise Equipment Co., Inc. $1,745,350.00
Northern Contracting Corp. $1,995,100.00
Paul J. Rogan Inc. $2,397,500.00